16
THE INVERCLYDE COUNCIL
LEISURE
AND CULTURAL SERVICES COMMITTEE
THURSDAY 15 JANUARY 1998 - 3.00pm
Present:- Provost Allan, Councillors Calvert, Morrison (M), Roach, Sir Simpson Stevenson and Hunter, Councillor Morrison (M), Convener, in the Chair.
In attendance:- The Assistant Chief Executive (Social and Community Development), the Director of Central Services, Mr C McCrone (for the Director of Finance), the Director of Leisure and Recreation, Mr D Stoddart (for the Director of Property and Technical Services) and Mr C Clelland (for the Director of Legal Services).
Apologies for absence were intimated on behalf of Councillors Robertson (A), Robertson (Y) and Finnie.
The following paragraphs are submitted for information only, having been dealt with under the powers delegated to the Committee.
53 CAPITAL PROGRAMME 1997/98 - TECHNICAL PROGRESS 53
SUBMITTED: Report dated 19 December 1997 by the Director of Property and Technical Services on the technical progress of the Capital Programme 1997/98.
NOTED
54 CAPITAL PROGRAMME 1997/98 - FINANCIAL PROGRESS 54
SUBMITTED: Report dated 18 December 1997 by the Director of Finance on the current position of the Capital Programme 1997/98.
DECIDED:
(a) That the contents of the report be noted; and
(b) That the Policy and Strategy Committee be requested to increase the Committee's Capital Programme Budget by £109,000.
55 UNALLOCATED SAVINGS 55
SUBMITTED: Report dated 23 December 1997 by the Director of Leisure and Recreation showing how the unallocated savings would be found in this financial year, amounting to £56,610 and identifying savings for 1998/99.
DECIDED:
(a) That the arrangements detailed in the report with regard to unallocated savings for 1997/98 be approved as follows:-
(i) VAT refund £32,090
(ii) Savings on recharge from Housing £23,600
(iii) Saving of payments to Clyde Muirshiel Park £902
Total Savings £56,610 ; and
(b) That the additional savings identified as part of the budget exercise for 1998/99 be approved as follows:-
(i) Reduction in the budget for waivers of rent £4,230
(ii) Saving on the rates bill for Battery Park Pavillion £5,100
(iii) Reduction in Tenants Halls expenditure £8,100
(iv) Increase in income £14,660
Total Savings £32,090
56 GREENOCK CUT - CONSERVATION PROJECT 56
SUBMITTED: Report dated 15 December 1997 by the Director of Leisure and Recreation seeking approval from the Committee for the ongoing development relating to the Greenock Cut Conservation Project.
DECIDED:
(a) That the ongoing development of the Greenock Cut Conservation Project be approved;
(b) That the consultants funded by the Scottish Natural Heritage be appointed to examine further the co-ordination of a lottery application and the Committee consider the outcome of this report in due course; and
(c) That the Leisure and Recreation Department co-ordinate the input from Inverclyde Council as a whole in relation to the project.
57 CLIENT REPORT 57
SUBMITTED: Report dated 23 December 1997 by the Director of Leisure and Recreation advising of the ground maintenance contractors performance in general terms, to identify ongoing works and to forecast items which will be addressed during the forthcoming months.
NOTED
58 GREENOCK WATERFRONT LEISURE COMPLEX UPDATE 58
SUBMITTED: Report dated 22 December 1997 by the Director of Leisure and Recreation on the progress of the Waterfront Leisure Complex both operationally and in relation to the remaining building defects.
DECIDED:
(a) That the contents of the report be noted; and
(b) That it be remitted to the Director of Leisure and Recreation to proceed directly with the defect repairs and charging costs against retention monies.
59 RESOLUTION: EXCLUSION OF PUBLIC AND PRESS 59
On the motion of the Convener it was agreed unanimously that, in terms of Section 50(A)(4) of the Local Government (Scotland) Act 1973 as amended, the public and press be excluded from the meeting during consideration of the undernoted items of business on the grounds that consideration of the items involved the likely disclosure of exempt information as defined in the respective paragraphs of Part I of Schedule 7(A) of the Act as are set opposite each item:-
Item Paragraph(s)
Greenock Waterfront Leisure Complex - Gas Supply Update 6 & 8
Leisure Management Facilities Statistical Information 9
60 GREENOCK WATERFRONT LEISURE COMPLEX - GAS SUPPLY UPDATE 60
SUBMITTED: Report dated 10 September 1997 by the Director of Legal Services on the present position regarding the supply of gas to the Waterfront Leisure Complex and advising of measures which will be taken to seek the recovery of costs from other parties.
NOTED
61 LEISURE MANAGEMENT FACILITIES STATISTICAL INFORMATION 61
SUBMITTED: Report dated 19 December 1997 by the Director of Leisure and Recreation advising of the number of users and associated income for facilities run under the Leisure Management Contract in the Department of Leisure and Recreation for the period from 6 October 1997 to 7 December 1997.
NOTED
LEIS-15JAN98\0
2
Leisure and
Cultural Services Committee - 15/1/98
LEIS-15JAN98\0